Рабочие листы
к вашим урокам
Скачать
1 слайд
Lessons From the
Columbia Disaster
“Safety & Organizational Culture”
2005 © American Institute of Chemical Engineers
“Presentation Rev_newv4_final” as of 11_15_05
2 слайд
FEB 1, 2003 8:59 EST
All 7 astronauts are killed
$4 billion spacecraft is destroyed
Debris scattered over 2000 sq-miles of Texas
NASA grounds shuttle fleet for 2-1/2 years
Space shuttle Columbia, re-entering Earth’s atmosphere at 10,000 mph, disintegrates
3 слайд
Columbia- The Physical Cause
Insulating foam separates from external tank 81 seconds after lift-off
Foam strikes underside of left wing, breaches thermal protection system (TPS) tiles
Superheated air enters wing during re-entry, melting aluminum struts
Aerodynamic stresses destroy weakened wing
4 слайд
A Flawed Decision Process
Foam strike detected in launch videos on Day 2
Engineers requested inspection by crew or remote photo imagery
to check for damage
Mission managers discounted foam strike significance
No actions were taken to confirm shuttle integrity or prepare contingency plans
5 слайд
Seventeen Years Earlier…
January 28, 1986, the shuttle Challenger explodes 73 seconds into its launch, killing all seven crew members
Investigation reveals that a solid rocket booster (SRB) joint failed, allowing flames to impinge on the external fuel tank
6 слайд
Challenger…
Liquid hydrogen tank explodes, ruptures liquid oxygen tank
Resulting massive explosion destroys the shuttle
7 слайд
The Legacy of Challenger
The Rogers Commission, which investigated the incident, determined:
The SRB joint failed when jet flames burned through both o-rings in the joint
NASA had long known about recurrent damage to o-rings
Increasing levels of o-ring damage had been tolerated over time
Based upon the rationale that “nothing bad has happened yet”
8 слайд
The Legacy… continued
The Commission also determined that:
SRB experts had expressed concerns about the safety of the Challenger launch
NASA’s culture prevented these concerns from reaching top decision-makers
Past successes had created an environment of
over-confidence within NASA
Extreme pressures to maintain launch schedules
may have prompted flawed decision-making
The Commission’s recommendations addressed an number of organizational, communications, and safety oversight issues
9 слайд
Columbia- The Organizational Causes
“In our view, the NASA organizational culture had as much to do with this accident as the foam.”
CAIB Report, Vol. 1, p. 97
NASA had received painful lessons about its culture from the Challenger incident
CAIB found disturbing parallels remaining at the time of the Columbia incident… these are the topic of this presentation
10 слайд
Columbia Key Issues
With little corroboration, management had become convinced that a foam strike was not, and could not be, a concern.
Why were serious concerns about the integrity of the shuttle, raised by experts within one day after the launch, not acted upon in the two weeks prior to return?
Why had NASA not learned from the lessons of Challenger?
11 слайд
Maintain Sense Of Vulnerability
Combat Normalization Of Deviance
Establish an Imperative for Safety
Perform Valid/Timely Hazard/Risk Assessments
Ensure Open and Frank Communications
Learn and Advance the Culture
Key Organizational Culture Findings
– What NASA Did Not Do
12 слайд
Maintaining a Sense of Vulnerability
“Let me assure you that, as of yesterday afternoon, the Shuttle was in excellent shape, … there were no major debris system problems identified….”
NASA official on Day 8
“The Shuttle has become a mature and reliable system … about as safe as today’s technology will provide.”
NASA official in 1995
13 слайд
Maintaining a Sense of Vulnerability
NASA’s successes (Apollo program, et al) had created
a “can do” attitude that minimized the consideration
of failure
Near-misses were regarded as successes of a robust system rather than near-failures
No disasters had resulted from prior foam strikes,
so strikes were no longer a safety-of-flight issue
Challenger parallel… failure of the primary o-ring demonstrated the adequacy of the secondary o-ring
to seal the joint
A weak sense of vulnerability can lead to taking future success for granted… and to taking greater risks
14 слайд
Combating Normalization of Deviance
“…No debris shall emanate from the critical zone of the External Tank on the launch pad or during ascent…”
Ground System Specification Book – Shuttle Design Requirements
After 113 shuttle missions, foam shedding, debris impacts, and TPS tile damage came to be regarded as only a routine maintenance concern
15 слайд
Combating Normalization of Deviance
“This history portrays an incremental descent into poor judgment.”
Diane Vaughan,
The Challenger Launch Decision
Each successful mission reinforced the perception that foam shedding was unavoidable…either unlikely to jeopardize safety or an acceptable risk
Foam shedding, which violated the shuttle design basis, had been normalized
Challenger parallel… tolerance of damage to the primary o-ring… led to tolerance of failure of the primary o-ring… which led to the tolerance of damage to the secondary o-ring… which led to disaster
16 слайд
Establish An Imperative for Safety
“When I ask for the budget to be cut,
I’m told it’s going to impact safety on
the Space Shuttle … I think that’s a
bunch of crap.”
Daniel S. Goldin,
NASA Administrator, 1994
The shuttle safety organization, funded by the programs it was to oversee, was not positioned to provide independent safety analysis
The technical staff for both Challenger and Columbia were put in the position of having to prove that management’s intentions were unsafe
This reversed their normal role of having to prove
mission safety
17 слайд
Establish An Imperative for Safety
International Space Station deadline 19 Feb 04
Desktop screensaver at NASA
As with Challenger, future
NASA funding required
meeting an ambitious launch
schedule
Conditions/checks, once
“critical,” were now waived
A significant foam strike on a recent mission was not resolved prior to
Columbia’s launch
Priorities conflicted… and production won over safety
18 слайд
Perform Valid/Timely
Hazard/Risk Assessments
“Any more activity today on the tile damage or are people just relegated to crossing their fingers and hoping for the best?”
Email Exchange at NASA
“… hazard analysis processes are applied inconsistently across systems, subsystems, assemblies, and components.”
CAIB Report, Vol. 1, p. 188
NASA lacked consistent, structured approaches for identifying hazards and assessing risks
Many analyses were subjective, and many action items from studies were not addressed
In lieu of proper risk assessments, many identified concerns were simply labeled as “acceptable”
Invalid computer modeling of the foam strike was conducted by “green” analysts
19 слайд
Ensure Open and Frank Communications
I must emphasize (again) that severe enough damage… could present potentially grave hazards… Remember the NASA safety posters everywhere around stating, “If it’s not safe, say so”? Yes, it’s that serious.
Memo that was composed but never sent
Management adopted a uniform mindset that foam strikes were not a concern and was not open to contrary opinions.
The organizational culture
Did not encourage “bad news”
Encouraged 100% consensus
Emphasized only “chain of command” communications
Allowed rank and status to trump expertise
20 слайд
Ensure Open and Frank Communications
Lateral communications between some NASA sites were also dysfunctional
Technical experts conducted considerable analysis of the situation, sharing opinions within their own groups, but this information was not shared between organizations within NASA
As similar point was addressed by the Rogers Commission on the Challenger incident
Management pushback can discourage, even intimidate, those seeking to share concerns.
21 слайд
Learn and Advance the Culture
CAIB determined that NASA had not learned from the lessons of Challenger
Communications problems still existed
Experts with divergent opinions still had difficulty getting heard
Normalization of deviance was still occurring
Schedules often still dominated over safety concerns
Hazard/risk assessments were still shallow
Abnormal events were not studied in sufficient detail, or trended to maximize learnings
22 слайд
… An Epilog
Shuttle Discovery was launched on 7/26/05
NASA had formed an independent Return To Flight (RTF) panel to monitor its preparations
7 of the 26 RTF panel members issued a minority report prior to the launch
Expressing concerns about NASA’s efforts
Questioning if Columbia’s lessons had been learned
23 слайд
… An Epilog
During launch, a large piece of foam separated from the external fuel tank, but fortunately did not strike the shuttle, which landed safely 14 days later
The shuttle fleet was once again grounded, pending resolution of the problem with the external fuel tank insulating foam
24 слайд
Turning Inward
- Our Industry -
25 слайд
Piper Alpha
On 7/6/1988, a series of explosions and fires destroyed the Piper Alpha oil platform
165 platform workers and 2 emergency responders were killed
61 workers survived by jumping into the North Sea
26 слайд
The Physical Cause
It is believed that a pump had been returned to service with its discharge relief valve removed for testing
The light hydrocarbon (condensate) that was released formed a vapor cloud and ignited
The resulting vapor cloud explosion ruptured oil export lines and ignited fires on the platform
27 слайд
The Physical Cause
Other interconnected platforms continued production, feeding the leaks on Piper Alpha
Ensuing fires breached high pressure natural gas inlet lines on the platform
The enormity of the resulting conflagration prevented any organized evacuation
28 слайд
The Organizational Causes
The official investigation report, written by Lord Cullen, faulted the company’s management of safety on Piper Alpha
The confusion leading to restarting the condensate pump resulted from failures to adhere to the permit to work (PTW) system
Daily monitoring and periodic audits had failed to identify the continuing dysfunction of the system
29 слайд
The Organizational Causes
Inadequate shift turnovers failed to communicate the status of the pump to the oncoming shift
Inadequate communications (and PTW system problems) had contributed to a fatality, and a civil conviction for the company, but remedial action had not been taken
The diesel fire pumps were in manual and, after the explosion, could not be reached by staff seeking to start them
A prior audit recommendation to stop this practice had not been implemented
30 слайд
The Organizational Causes
Even if fire water had been available, many deluge nozzles were plugged
The company had been trying to resolve this problem for at least four years, but repairs were behind schedule
One year earlier, an engineering study had concluded that the gas risers were vulnerable and that a massive gas release could prevent successful evacuation of
the platform
Management had discounted the study results
31 слайд
The Organizational Causes
Other problems that audits and management reviews had failed to identify and/or resolve included:
Emergency response training given to workers new to the platform was cursory and often omitted. Some workers had not been shown the location of their life boat.
Platform managers had not been trained on how to respond to emergencies on other platforms (e.g., when to stop production)
Evacuation and emergency shutdown drills on Piper Alpha were not conducted according to schedule
32 слайд
Parallels to NASA and Columbia
Each Piper Alpha organizational cause can be mapped to one or more of the NASA lessons
Maintain Sense Of Vulnerability
Combat Normalization Of Deviance
Establish an Imperative for Safety
Perform Valid/Timely Hazard/Risk Assessments
Ensure Open and Frank Communications
Learn and Advance the Culture
33 слайд
Flixborough
On 6/1/1974, a massive vapor cloud explosion (VCE) destroyed a UK chemical plant
Consequences:
28 employees died and 36 were injured
Hundreds of off-site injuries
Approx. 1800 homes and 170 businesses damaged
34 слайд
The Physical Cause
Approx. 30 tons of boiling cyclohexane released from reactor system
Most likely release cause was the failure of a temporary piping modification
Installed between two reactors
Was a bypass for reactor removed for repairs
35 слайд
The Physical Cause
Bellows not designed for 38-ton thrust
Design standards for bellows ignored
Inadequate pressure test of installation
Inadequate vertical and lateral support for jumper
36 слайд
The Organizational Causes
No qualified mechanical engineer on-site
Inadequate concern with the cause of the reactor failure
Jumper connection considered a routine plumbing job
No detailed design for jumper
37 слайд
The Organizational Causes
“Hurry up”
attitude of management
Overworked staff did not take time to properly analyze their actions
38 слайд
Parallels to NASA and Columbia
Each Flixborough organizational cause can be mapped to one or more of the following NASA lessons
Maintain Sense Of Vulnerability
Establish an Imperative for Safety
Perform Valid/Timely Hazard/Risk Assessments
39 слайд
Could this happen to us?
Optional: Paste Company logo here
Complacency due to our superior safety performance
Normalizing our safety critical requirements
Ineffective Risk Assessments of our systems
Reversing the Burden of Proof when evaluating safety of operations
Employees Not Speaking Freely of their safety concerns
Business Pressures at odds with safety priorities
Failure to Learn and apply learnings to improving our culture
40 слайд
Title for Relevant Company Event
Use this section to briefly summarize key aspects of the event
Do not addresses causes here
Add additional slides if required
Paste photo related to event in space at right, if desired
JPG files at 300 dpi, provide adequate resolution
If photo is not provided, drag right border over to expand this text box
Optional: Paste Company logo here
41 слайд
The Physical Cause
Briefly describe the factors that caused the event
Do not address organizational factors here
Add additional slides if required
Add photo to the right, or expand the text box as desired/needed
Optional: Paste Company logo here
42 слайд
The Organizational Causes
Describe the organizational causes of the event
Where feasible, lay a basis for parallels to the 6 NASA organizational culture findings
Maintain Sense Of Vulnerability
Combat Normalization Of Deviance
Establish an Imperative for Safety
Perform Appropriate and Timely Hazard/Risk Assessments
Ensure Open and Frank Communications
Learn and Advance the Culture
Optional: Paste Company logo here
43 слайд
Parallels to NASA and Columbia
If you feel that this would add to the emphasis of the message, include one or more slides that emphasize how your organizational causes relate to the underlying themes from Columbia
Alternatively, you may want to leave this as an individual or group exercise for the audience
Optional: Paste Company logo here
44 слайд
Indicators Of Organizational Culture Weaknesses
The following slides provide examples of indicators that your organization is…
45 слайд
…NOT Maintaining a
Sense of Vulnerability
Safety performance has been good… and you do not recall the last time you asked “But what if…?”
You assume your safety systems are good enough
You treat critical alarms as operating indicators
You allow backlogs in preventative maintenance of critical equipment
Actions are not taken when trends of similar deficiencies are identified.
46 слайд
…NOT Preventing
Normalization of Deviance
You allow operations outside established safe operating limits without detailed risk assessment
Willful, conscious, violation of an established procedure is tolerated without investigation, or without consequences for the persons involved
Staff cannot be counted on to strictly adhere to safety policies and practices when supervision is not around to monitor compliance
You are tolerating practices or conditions that would have been deemed unacceptable a year or two ago
47 слайд
…NOT Establishing An
Imperative for Safety
Staff monitoring safety related decisions are not technically qualified or sufficiently independent
Key process safety management positions have been downgraded over time or left vacant
Recommendations for safety improvements are resisted on the grounds of cost or schedule impact
No system is in place to ensure an independent review of major safety-related decisions
Audits are weak, not conducted on schedule, or are regarded as negative or punitive and, therefore, are resisted
48 слайд
…NOT Performing Valid/Timely
Hazard/Risk Assessments
Availability of experienced resources for hazard or risk assessments is limited
Assessments are not conducted according to schedule
Assessments are done in a perfunctory fashion, or seldom find problems
Recommendations are not meaningful and/or are not implemented in a timely manner
Bases for rejecting risk assessment recommendations are mostly subjective judgments or are based upon previous experience and observation.
49 слайд
…NOT Ensuring Open and
Frank Communications
The bearer of “bad news” is viewed as “not a team player”
Safety-related questioning “rewarded” by requiring the suggested to prove he / she is correct
Communications get altered, with the message softened, as they move up or down the management chain
Safety-critical information is not moving laterally between work groups
Employees can not speak freely, to anyone else, about their honest safety concerns, without fear of career reprisals.
50 слайд
…NOT Learning and Advancing
the Culture
Recurrent problems are not investigated, trended, and resolved
Investigations reveal the same causes recurring time and again
Staff expresses concerns that standards of performance are eroding
Concepts, once regarded as organizational values, are now subject to expedient reconsideration
51 слайд
“Engineering By View Graph”
“When engineering analyses and risk assessments are condensed to fit on a standard form or overhead slide, information is inevitably lost… the priority assigned to information can be easily misrepresented by its placement on a chart and the language that is used.”
CAIB Report, Vol. 1, p. 191
The CAIB faulted shuttle project staff for trying to summarize too much important information on too few PowerPoint slides
We risk the same criticism here
This presentation introduces the concept of organizational effectiveness and safety culture, as exemplified by the case studies presented
This is only the beginning…
Рабочие листы
к вашим урокам
Скачать
6 655 322 материала в базе
Настоящий материал опубликован пользователем Шпак Анжелика Геннадьевна. Инфоурок является информационным посредником и предоставляет пользователям возможность размещать на сайте методические материалы. Всю ответственность за опубликованные материалы, содержащиеся в них сведения, а также за соблюдение авторских прав несут пользователи, загрузившие материал на сайт
Если Вы считаете, что материал нарушает авторские права либо по каким-то другим причинам должен быть удален с сайта, Вы можете оставить жалобу на материал.
Удалить материалВаша скидка на курсы
40%Курс повышения квалификации
36 ч.
Курс повышения квалификации
72 ч. — 180 ч.
Курс повышения квалификации
72 ч. — 180 ч.
Мини-курс
6 ч.
Мини-курс
8 ч.
Оставьте свой комментарий
Авторизуйтесь, чтобы задавать вопросы.